A14 Bologna – Taranto Motorway

Value: approximately EUR 61 M
Completion of works: January 2013
Planned duration of works: 3 years and 6 months
Actual duration of works: 2 years and 10 months
Main interventions: Scacciano Natural Tunnel (300 m) - Scacciano Temporary Artificial Tunnel (Bretella) (261.50 m)



Works to enlarge the third carriageway - LOT 1A
section: North Rimini – Cattolica